Description:
This project involves the removal and replacement of approximately 1,200 s.y. of 4" PCC and 60 s.y. of 6" PCC sidewalk located at multiple sites in Iowa City.
Project Schedule Information:
Specified Start Date: July 15, 2020
Substantial Completion Date: October 30, 2020
Final Completion Date: November 30, 2020
Liquidated Damages: $50 per day
Date plans available:
Friday, June 12, 2020
Obtain from:
Technigraphics / Rapids Reproductions
415 Highland Ave, Suite 100
Iowa City, Iowa 52240
(319) 354-5950
Cost:
None
Pre-bid Conference:
None