Description:
This project includes replacement and repair of sanitary sewers and reconnection of sanitary sewer services at eight (8) locations across the City of Iowa City.
Project Schedule Information:
Working days: 10 days per location
Start date: November 1, 2018
Substantial Completion Date: April 30, 2019
Final Completion Date: May 31, 2019
Liquidated damages: $250 per day after exceeding ten (10) work days at a single location or after exceeding the Final Completion Date, May 31, 2019
Date plans available:
Monday, October 8, 2018
Obtain from:
Rapids Reproductions / Technigraphics
415 Highland Avenue
Iowa City, IA 52240
319-354-5950
iowacity@rapidsrepro.com
Cost:
None
Pre-bid Conference:
Date: Wednesday, October 17, 2018
Time: 10:30 a.m.
Location: Engineering Conference Room, City Hall, 410 E Washington Street, Iowa City, Iowa