Description:
Remove 31 l.f. of 18" VCP storm sewer pipe and replace with 31 l.f. of 18" RCP. Remove and replace 153 s.y. PCC pavement. Remove and replace 100 s.y. of 6" PCC driveway and 13 s.y. of 4" PCC sidewalk.
Project Schedule Information:
Working Days: 26
Late Start Date: October 22, 2105
Liquidated Damages: $250 per day
Date plans available:
Wednesday, September 23, 2015
Obtain from:
Engineering Division
City of Iowa City
410 E Washington Street
Iowa City, IA 52240
319-356-5140
Cost:
$0
Pre-bid Conference:
None