The project includes the construction of new water main and ADA and sidewalk improvements along Clinton Street between Court Street and Burlington Street, the construction of new turn lanes and signal improvements at the Burlington Clinton intersection, and the restriping of Clinton Street to include a 4-land to 3-lane conversion and the addition of bike lanes within the Clinton Street corridor.
Working Days: 75
Specified Start Date: July 10, 2017
Liquidated Damages: $500 per day
Rapids Reproductions
415 Highland Avenue
Iowa City, IA 52240
319-354-5950
$30 fee per plan set - Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project
$15 non-refundable shipping fee if mailed
Date: May 18, 2017
Time: 2:00 p.m.
Location: Engineering Conference Room
City Hall
410 E Washington St.
Iowa City, IA