The Burlington and Madison Intersection Improvements Project includes the widening of Burlington Street from Madison Street to Front Street to include continuous buffered bike lanes from Madison Street to Riverside Drive. The project also includes traffic signal and pedestrian signal improvements, ADA sidewalk improvements, and public utility improvements at the Burlington Street and Madison Street intersection.

Project Schedule Information: 

Approximate Start Date:  April 1, 2019
Completion Date:  August 28, 2020
Liquidated Damages:  $1,500 per day

Date plans available: 
Tuesday, November 19, 2019
Obtain from: 

A listing of projects open for bids and details for each project will be available to potential bidders and suppliers three weeks prior to the letting date at www.bidx.com/is/main or www.iowadot.gov or by calling the Office of Contracts at 515-239-1414.

The Iowa DOT uses www.bidx.com as the official depository for bid submittal. Unless otherwise specified, bidders shall submit an electronic proposal with digital signature using the bidding software furnished by the Iowa DOT and electronic bid submittal procedures of the Iowa DOT.

Cost: 

None

Pre-bid Conference: 

N/A

Project Status

Awarded

Awardee

Vieth Construction

Engineer's Estimate

$1,400,000

Bid Deadline

Tuesday, December 17, 2019 - 10:00am

Council Award Date

Tuesday, January 7, 2020