This project includes modifications and upgrades to temperature control systems at City Hall, Robert A. Lee Recreation Center, and Mercer Aquatic Center and Scanlon Gymnasium for the purpose of integrating existing HVAC systems into the City’s existing Building Automation System. Included is related mechanical and electrical work.
Construction Start Date: Robert A Lee Rec Center and Mercer Aquatic Center - January 15, 2018
City Hall - July 14, 2018
Substantial Completion Date: Robert A Lee Rec Center and Mercer Aquatic Center - June 15, 2018
City Hall - December 14, 2018
Final Completion Date: Robert A Lee Rec Center and Mercer Aquatic Center - July 13, 2018
City Hall - January 11, 2019
Technigraphics / Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
$30 deposit per plan set and $15 fee if plan set is shipped.
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Date: November 30, 2017
Time: 10:00 a.m
Location: Emma J Harvat Hall, City Hall, 410 E Washington St., Iowa City, Iowa
Project Status
Awardee
No Bids Received