The Project will involve the following: General construction at the City of Iowa Wastewater Treatment Plant, 4366 Napoleon Street SE, Iowa City, IA. Work will include demolition of three existing belt filter presses, procurement and installation of three new belt filter presses with associated modifications of floor slab, mechanical piping and electrical systems, conversion of two window sets to coil doors, replacement of three belt filter press feed pumps and associated piping, replacement of four polymer pumps; replacement of HVAC exhaust fans.
Milestone 1 Date: January 12th, 2018
Substantial Completion Date: May 1st, 2018
Specified Completion Date: May 31, 2018
Specified Start Date: November 2, 2017
Liquidated Damages: $500 per day
Stanley Consultants, Inc.
225 Iowa Avenue
Muscatine, IA 52761
563-264-6657
Date: September 28, 2017
Time: 10:00 a.m.
Location: Wastewater Treatment Facility, 4366 Napoleon Street SE, Iowa City, Iowa