The project involves the resurfacing of various city streets. Major bid items include: 1,953 tons of asphalt cement concrete; 11,979 sy of pavement milling; 439 ft. of pcc curb and gutter replacement; 539 sy of pcc sidewalk and curb ramp pavement removal and replacement; 187 sy of HMA patching; 1,442 sy of PCC patching; 3,911 gal. of chip sealing binder; 196 tons of chip seal cover aggregate; traffic control; and other related work.
Phase 1: Street Milling and Overlay
Early Start: June 15, 2015
Completion Date: July 24, 2015
Liquidated Damages: $500 per day
Phase 2: Chipseal surfacing
Early Start: June 15, 2015
Completion Date: August 31, 2015
Liquidated Damages: $500 per day
Engineering Division
City of Iowa City
410 E. Washington Street
Iowa City, Iowa 52240
319-356-5140
$25 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.