Description: 

The Asphalt Resurfacing 2019 Project includes pavement milling and asphalt resurfacing along South Clinton Street, Fairmeadows Avenue, Newton Road, Valley Avenue, South Gilbert Street, Park Road and Ferson Avenue intersection, and the City Equipment Parking Lot. In addition to the resurfacing, this project also includes storm intake repairs, repair of curb and gutter, replacement of curb ramps to meet current ADA standards, and new pavement markings on Dodge Street to include a one-way to two‑way conversion from Burlington Street to Bowery Street and a 4-lane to 3-lane conversion from Bowery Street to Kirkwood Avenue. This project also includes street sealcoat work along Taft Avenue.

Project Schedule Information: 

Specified start date:  August 5, 2019

Final completion date: November 1, 2019

Liquidated damages: $500 per day

 

Date plans available: 
Wednesday, June 19, 2019
Obtain from: 

Technigraphics / Rapids Reproductions

415 Highland Ave, Suite 100

Iowa City, Iowa 52240

Cost: 

$25 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

A non-mandatory Pre-Bid Meeting will be held on July 2, 2019 at 10:30 a.m. in the Engineering Conference Room, City Hall, 410 East Washington Street, Iowa city, Iowa 52240.

Project Status

Under Review

Engineer's Estimate

$1,480,000

Bid Deadline

Wednesday, July 10, 2019 - 3:00pm