The Project will involve pavement milling and resurfacing, and ADA curb ramp replacement along Benton Street, Market Street, and Sheridan Street in Iowa City. This work will include the following estimated quantities: 3,387 tons of asphalt cement concrete, 16,613 sq. yards of pavement milling, 2,245 feet of pcc curb and gutter replacement, 1,827 sq. yards of pcc sidewalk and curb ramp pavement removal and replacement, installation of 2 intakes and 1 storm manhole, installation of 45 feet of storm sewer piping. The Project will also include street sealcoat work along St Clemens Street, Scott Park, Taft Avenue, and Gilbert St. Ct. in Iowa City. This work will include the following estimated quantities: 3,877 GAL. of chip sealing binder, 179 tons of chip seal cover aggregate, traffic control, other related work.
Phase 1: Street Milling and Overlay (Benton Street, Market Street, Sheridan Avenue)
Early Start: May 15, 2017 - - (Market Street Only)
Early Start: June 19, 2017 - - (Benton Street, Sheridan Avenue)
Late Start: June 19, 2017 - - All Locations
Completion Deadline: August 11, 2017
Phase 2: Chipseal Surfacing
Early start: July 1, 2017
Completion Deadline: August 31, 2017
Liquidated Damages: $500 per day
Rapids Reproductions / Technigraphics
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
$25 per plan set
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
None