Description:
The Project will involve the following: Upgrading door access control at the Wastewater Treatment Plant (WWTP), City Hall (CH), and Water Plant (WP), which includes work to provide electric door hardware, provide conduit pathways, provide low voltage cabling, and provide electronic access control hardware.
Project Schedule Information:
Start Date: January 17, 2022
Substantial Completion: March 18, 2022
Final Completion: April 1, 2022
Liquidated Damages: $250 per day
Date plans available:
Wednesday, December 1, 2021
Obtain from:
Rapids Reproduction, Inc.
415 Highland Ave.
Iowa City, IA 52240
Phone: (319) 354-5950
iowacity@rapidsrepro.com
Cost:
None
Pre-bid Conference:
Date: December 8, 2021
Time: 10:00am
Location: City Hall, 410 East Washington Street, Iowa City, Iowa, Helling Conference Room