Description: 

This project includes pavement repairs associated with water main breaks on various streets throughout Iowa City. Types of pavement that need repaired include: Portland Cement Concrete (PCC); composite pavement consisting of PCC and Hot Mix Asphalt (HMA); and full depth HMA pavement. Some locations will also require the removal and replacement of driveway, sidewalk, curb ramps, and/or curb and gutter.

Project Schedule Information: 

Specified start date:  July 26, 2022
Substantial completion date:  October 28, 2022
Final completion date:  November 30, 2022
Liquidated damages:  $500 per day

Date plans available: 
Tuesday, June 7, 2022
Obtain from: 

Technigraphics/Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Bockenstedt Excavating

Engineer's Estimate

$175,000

Bid Deadline

Tuesday, June 28, 2022 - 3:00pm

Council Award Date

Tuesday, July 12, 2022