Description:
This project includes pavement repairs associated with water main breaks on various streets throughout Iowa City. Types of pavement that need repaired include: Portland Cement Concrete (PCC); composite pavement consisting of PCC and Hot Mix Asphalt (HMA); and full depth HMA pavement. Some locations will also require the removal and replacement of driveway, sidewalk, curb ramps, and/or curb and gutter.
Project Schedule Information:
Specified start date: July 26, 2022
Substantial completion date: October 28, 2022
Final completion date: November 30, 2022
Liquidated damages: $500 per day
Date plans available:
Tuesday, June 7, 2022
Obtain from:
Technigraphics/Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
Cost:
None
Pre-bid Conference:
None