Description: 

The Project will involve the following restriping of 5.5 foot bike lanes with a 2 foot buffer on Market Street and Jefferson Street, Keokuk street will include a 5.5 foot bike lane, and Southgate Avenue will have a 5.5 foot bike lane with a 1.5 foot buffer.

Project Schedule Information: 

Early Start Date: October 31, 2022
Late Start Date: May 1, 2023
Substantial Completion: June 2, 2023
Final Completion: June 16, 2023
Liquidated Damages: $250 per day

Date plans available: 
Wednesday, September 21, 2022
Obtain from: 

Technigraphics, a division of Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, Iowa 52240

Phone: (319) 354-5950
Toll-Free: (800) 779-0093
https://rapidsrepro.com/iowa-city/

Cost: 

None

Pre-bid Conference: 

Date:  October 4, 2022
Time:  3:00 p.m.
Location:  Engineering Conference Room - 3rd Floor, City Hall, 410 E Washington Street, Iowa City, Iowa

Project Status

Awarded

Awardee

LL Pelling Company

Engineer's Estimate

$90,000

Bid Deadline

Tuesday, October 11, 2022 - 3:00pm

Council Award Date

Tuesday, October 18, 2022

Contact