Description: 

Reconstruction of Rochester Avenue from the bridge at Ralston Creek to just east of 1st Avenue.  The project will provide two 10-foot lanes from Ralston Creek to Rita Lyn Court and three 10’ lanes from Rita Lyn Court to 1st Avenue with 6.5-foot bicycle lanes and associated buffers.  Construction will include 4,000 linear feet of storm sewer, 3,700 linear feet of water main and installation of a pressure reducing valve and vault, 17,000 square yards of concrete pavement, sidewalk improvements, cast in place retaining walls, traffic signals, street lighting and restoration.

Project Schedule Information: 

Specified Start Date:  July 5, 2022
Milestone #1 Completion Date:  December 22, 2023
Substantial Completion Date:  June 28, 2024
Final Completion Date: September 30, 2024
Liquidated damages:  $1,000 per day

Date plans available: 
Wednesday, May 4, 2022
Obtain from: 

Rapids Reproduction, Inc.
415 Highland Ave.
Iowa City, IA 52240
Phone: (319) 354-5950
iowacity@rapidsrepro.com

Cost: 

None

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

Boomerang Corporation

Engineer's Estimate

$5,600,000

Bid Deadline

Tuesday, May 24, 2022 - 3:00pm

Council Award Date

Monday, June 6, 2022

Contact