Reconstruction of Rochester Avenue from the bridge at Ralston Creek to just east of 1st Avenue. The project will provide two 10-foot lanes from Ralston Creek to Rita Lyn Court and three 10’ lanes from Rita Lyn Court to 1st Avenue with 6.5-foot bicycle lanes and associated buffers. Construction will include 4,000 linear feet of storm sewer, 3,700 linear feet of water main and installation of a pressure reducing valve and vault, 17,000 square yards of concrete pavement, sidewalk improvements, cast in place retaining walls, traffic signals, street lighting and restoration.
Specified Start Date: July 5, 2022
Milestone #1 Completion Date: December 22, 2023
Substantial Completion Date: June 28, 2024
Final Completion Date: September 30, 2024
Liquidated damages: $1,000 per day