Description: 

The project includes pavement repairs associated with water main breaks on various streets throughout Iowa City. Types of pavement that need repaired include Portland Cement Concrete (PCC), PCC with Hot Mix Asphalt (HMA) overlay, and full depth HMA. Some locations will also require the removal and replacement of driveway, sidewalk, and/or curb and gutter.

Project Schedule Information: 

Specified Start Date:  June 28, 2021
Working Days per Location:  Five (5)
Substantial Completion Date: October 29, 2021
Final Completion Date:  November 19, 2021
Liquidated Damages:  $500 per day after exceeding five (5) working days at a single location or after either of the completion dates

Date plans available: 
Wednesday, May 19, 2021
Obtain from: 

Technigraphics/Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
800-779-0093

Cost: 

$20 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

All American Concrete

Engineer's Estimate

$132,000

Bid Deadline

Tuesday, June 8, 2021 - 3:00pm

Council Award Date

Tuesday, June 15, 2021

Contact

Document(s)