Description:
The supply and installation of street trees along Foster Road, Mackinaw Drive, Sugar Loaf Circle, Manitou Trail, Tranquil Bluff Trail, Mission Point Road, Arch Rock Road, Algonquin Road and Scott Boulevard.
Project Schedule Information:
Specified Start Date: May 17, 2021
Final Completion Date: November 15, 2021
Liquidated Damages: $250.00 per day
Date plans available:
Wednesday, March 17, 2021
Obtain from:
Rapids Reproductions, Inc./Technigraphics
415 Highland Avenue Suite 100
Iowa City, IA 52240
319-354-5950
Cost:
$20 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Pre-bid Conference:
None