Description: 

Pavement repairs associated with water main breaks on various streets throughout Iowa City. Types of pavement that need repaired include: Portland Cement Concrete (PCC); composite pavement consisting of PCC and Hot Mix Asphalt (HMA); and brick with a PCC base.  Some locations will also require the removal and replacement of driveway, sidewalk, and/or curb and gutter.

Project Schedule Information: 

Specified Start Date:  June 1, 2020
Working Days per Location:  Five (5)
Substantial Completion Date:  September 30, 2020
Final Completion Date:  October 30, 2020
Liquidated Damages:  $500 per day after exceeding five (5) working days at a single location or after either of the completion dates

Date plans available: 
Wednesday, April 22, 2020
Obtain from: 

Technigraphics / Rapids Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA  52240
319-354-5950
800-779-0093
 

Cost: 

$20 per plan set.  Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.

Pre-bid Conference: 

None

Project Status

Awarded

Awardee

All American Concrete

Engineer's Estimate

$150,000

Bid Deadline

Tuesday, May 19, 2020 - 10:30am

Council Award Date

Tuesday, May 19, 2020