Description:
This project includes the lining of 1,063 LF of 24-inch diameter sewer pipe, 2,704 LF of 12-inch diameter sewer pipe, 4247 LF of 8-inch diameter sewer pipe, 116 service connection reinstatements and other associated lining work and is located at various locations across Iowa City.
Project Schedule Information:
Specified Start Date: January 2, 2019
Substantial Completion: March 1, 2019
Final Completion: April 15, 2019
Liquidated Damages: $500 per day
Date plans available:
Wednesday, November 21, 2018
Obtain from:
Technigraphics / Rapid Reproductions
415 Highland Avenue, Suite 100
Iowa City, IA 52240
319-354-5950
Cost:
$30 per plan set. Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
Pre-bid Conference:
None