Preparation, paving of roadway and sidewalk, curbs, site improvements, planting, site utilities in Washington Street from Clinton Street to Linn Street.
Phase 1:
Early Start Date: April 11, 2016
Substantial Completion Date: July 23, 2016
Incentive/Disincentive: $1,000 per day
Maximum Incentive: $10,000
Phase 2:
Substantial Completion Date: September 30, 2016
Incentive/Disincentive: $3,000 per day
Maximum Incentive: $45,000
Final Completion Date: October 21, 2016
Liquidated Damages: $500 per day
Technigraphics
415 Highland Avenue #100
Iowa City, Iowa 52240
319-354-5950
$50 per plan set
Deposit refundable if plans/specifications are returned in reusable condition within 14 days of reward of project.
A non-mandatory Pre-Bid meeting will be held. Prospective bidders in attendance will be guided through the vault interiors from approximately 2:30 p.m. to 5:00 p.m.
Date: February 4, 3016
Time: 1:30 p.m.
Location: Eamma J Harvat Hall, City Hall, 410 E Washington Street, Iowa City, Iowa